Time and Work – 50 Questions with Answers (समय और कार्य – 50 प्रश्न उत्तर सहित)
Answer: Work done in 4 days = (4/12) = 1/3 of the work.
उत्तर: 4 दिनों में किया गया कार्य = (4/12) = कार्य का 1/3 भाग।
Answer: Work/day by A = 1/20, by B = 1/30; Together = 1/20 + 1/30 = (3+2)/60 = 5/60 = 1/12; Time taken = 12 days.
उत्तर: A का दैनिक कार्य = 1/20, B का = 1/30; मिलकर = 1/20 + 1/30 = (3+2)/60 = 5/60 = 1/12; समय = 12 दिन।
Answer: Work/day = 60%/9 = 20% per day; So, time = 100% / 20% = 5 days.
उत्तर: दैनिक कार्य = 60%/9 = 20% प्रति दिन; तो समय = 100% / 20% = 5 दिन।
Answer: Work done by A in 5 days = 5/15 = 1/3; Remaining work = 2/3; Work/day together = 1/15 + 1/10 = (2+3)/30 = 5/30 = 1/6; Time to finish = (2/3) ÷ (1/6) = 4 days; Total time = 5 + 4 = 9 days.
उत्तर: A द्वारा 5 दिन में किया गया कार्य = 5/15 = 1/3; शेष कार्य = 2/3; साथ में दैनिक कार्य = 1/15 + 1/10 = (2+3)/30 = 5/30 = 1/6; शेष कार्य पूरा करने में समय = (2/3) ÷ (1/6) = 4 दिन; कुल समय = 5 + 4 = 9 दिन।
Answer: Work/day by A = 1/24, B = 1/16. In two days, work done = 1/24 + 1/16 = (2/48 + 3/48) = 5/48. Days needed for full work = 48/5 × 2 = 19.2 days (approximately 20 days).
उत्तर: A का दैनिक कार्य = 1/24, B का = 1/16. दो दिनों में कार्य = 1/24 + 1/16 = (2/48 + 3/48) = 5/48. पूर्ण कार्य के लिए दिन = 48/5 × 2 = 19.2 दिन (लगभग 20 दिन)।
Answer: Work/day = 1/18 + 1/24 + 1/36 = (4/72 + 3/72 + 2/72) = 9/72 = 1/8; Time = 8 days.
उत्तर: दैनिक कार्य = 1/18 + 1/24 + 1/36 = (4/72 + 3/72 + 2/72) = 9/72 = 1/8; समय = 8 दिन।
Answer: Since A is twice efficient, A will take 12/2 = 6 days.
उत्तर: चूंकि A दुगना कुशल है, A का समय = 12/2 = 6 दिन।
Answer: B’s efficiency = 1.5 × A; So, time taken by B = 15 / 1.5 = 10 days.
उत्तर: B की दक्षता = 1.5 × A; इसलिए B का समय = 15 / 1.5 = 10 दिन।
Answer: Work/day A+B = 1/10, B = 1/15; So, A = 1/10 – 1/15 = (3-2)/30 = 1/30; Time taken by A = 30 days.
उत्तर: A+B का दैनिक कार्य = 1/10, B = 1/15; इसलिए A = 1/10 – 1/15 = (3-2)/30 = 1/30; A का समय = 30 दिन।
Answer: Filling rate = 1/20 + 1/30 = (3+2)/60 = 5/60 = 1/12; Time to fill = 12 minutes.
उत्तर: भरने की दर = 1/20 + 1/30 = (3+2)/60 = 5/60 = 1/12; भरने का समय = 12 मिनट।
Answer: Work/day = 1/10 + 1/15 + 1/20 = (6+4+3)/60 = 13/60; Work done in 2 days = 2 × 13/60 = 26/60 = 13/30; Remaining = 1 – 13/30 = 17/30.
उत्तर: दैनिक कार्य = 1/10 + 1/15 + 1/20 = (6+4+3)/60 = 13/60; 2 दिन में कार्य = 2 × 13/60 = 26/60 = 13/30; बचा कार्य = 1 – 13/30 = 17/30।
Answer: Work/day B+C = 1/12 + 1/24 = (2+1)/24 = 3/24 = 1/8; Work done in 3 days = 3 × 1/8 = 3/8; Remaining work = 5/8; Work/day A+B+C = 1/8 + 1/12 + 1/24 = (3+2+1)/24 = 6/24 = 1/4; Time to finish = (5/8) ÷ (1/4) = 2.5 days; Total = 3 + 2.5 = 5.5 days.
उत्तर: दैनिक कार्य B+C = 1/12 + 1/24 = (2+1)/24 = 3/24 = 1/8; 3 दिन में कार्य = 3 × 1/8 = 3/8; बचा कार्य = 5/8; दैनिक कार्य A+B+C = 1/8 + 1/12 + 1/24 = (3+2+1)/24 = 6/24 = 1/4; पूरा करने का समय = (5/8) ÷ (1/4) = 2.5 दिन; कुल = 3 + 2.5 = 5.5 दिन।
Answer: Let B’s time = x days, A’s time = 2x; Work/day A+B = 1/x + 1/2x = 3/2x; 3/2x = 1/12 → x = 18 days.
उत्तर: मान लें B का समय = x दिन, A = 2x; दैनिक कार्य A+B = 1/x + 1/2x = 3/2x; 3/2x = 1/12 → x = 18 दिन।
Answer: Let B’s time = x days; A’s time = x/3; Work/day A+B = 1/x + 3/x = 4/x = 1/8; So, x = 32 days.
उत्तर: मान लें B का समय = x दिन; A का समय = x/3; दैनिक कार्य A+B = 1/x + 3/x = 4/x = 1/8; इसलिए x = 32 दिन।
Answer: Let slower person’s time = x days; faster person = x/2; Together work/day = 1/x + 2/x = 3/x = 1/9; So, x = 27 days; Faster person = 27/2 = 13.5 days.
उत्तर: मान लें धीमे व्यक्ति का समय = x दिन; तेज़ व्यक्ति = x/2; मिलकर कार्य/दिन = 1/x + 2/x = 3/x = 1/9; तो x = 27 दिन; तेज़ व्यक्ति = 27/2 = 13.5 दिन।
Answer: B’s time = 20 / 1.25 = 16 days.
उत्तर: B का समय = 20 / 1.25 = 16 दिन।
Answer: Work done by A in 4 days = 4/12 = 1/3; Remaining work = 2/3; Work/day A+B = 1/12 + 1/16 = (4+3)/48 = 7/48; Time to finish = (2/3) ÷ (7/48) = (2/3) × (48/7) = 32/7 ≈ 4.57 days; Total time = 4 + 4.57 = 8.57 days.
उत्तर: A द्वारा 4 दिन में किया गया कार्य = 4/12 = 1/3; बचा कार्य = 2/3; A+B का दैनिक कार्य = 1/12 + 1/16 = (4+3)/48 = 7/48; पूरा करने का समय = (2/3) ÷ (7/48) = (2/3) × (48/7) = 32/7 ≈ 4.57 दिन; कुल समय = 4 + 4.57 = 8.57 दिन।
Answer: Work/day A = 1/15; A+B+C = 1/6; So B+C = 1/6 – 1/15 = (5-2)/30 = 3/30 = 1/10; So B and C together take 10 days.
उत्तर: A का दैनिक कार्य = 1/15; A+B+C = 1/6; तो B+C = 1/6 – 1/15 = (5-2)/30 = 3/30 = 1/10; B और C साथ में 10 दिन लेंगे।
Answer: A’s rate = 1/18; B’s rate = 2 × 1/18 = 1/9 but B works half the time, so effective work/day = (1/9) × (1/2) = 1/18; Both finish at the same time.
उत्तर: A की दर = 1/18; B की दर = 2 × 1/18 = 1/9 लेकिन आधा समय काम करता है, प्रभावी कार्य/दिन = (1/9) × (1/2) = 1/18; दोनों एक ही समय में पूरा करेंगे।
Answer: Work done in first 12 minutes = 12(1/24 + 1/36) = 12(3/72 + 2/72) = 12(5/72) = 5/6; Remaining = 1 – 5/6 = 1/6; Filled by first pipe alone = 1/24 per minute; Time = (1/6) ÷ (1/24) = 4 minutes; Total time = 12 + 4 = 16 minutes.
उत्तर: पहले 12 मिनट में कार्य = 12(1/24 + 1/36) = 12(3/72 + 2/72) = 12(5/72) = 5/6; बचा = 1 – 5/6 = 1/6; पहले पाइप की दर = 1/24 प्रति मिनट; समय = (1/6) ÷ (1/24) = 4 मिनट; कुल समय = 12 + 4 = 16 मिनट।
Answer: Work/day A+B = 1/24 + 1/18 = (3+4)/72 = 7/72; Work done in 6 days = 6 × 7/72 = 7/12; Remaining = 1 – 7/12 = 5/12.
उत्तर: दैनिक कार्य A+B = 1/24 + 1/18 = (3+4)/72 = 7/72; 6 दिन में किया गया कार्य = 6 × 7/72 = 7/12; बचा कार्य = 1 – 7/12 = 5/12।
Answer: B’s time = 30 / 2 = 15 days.
उत्तर: B का समय = 30 / 2 = 15 दिन।
Answer: Let time taken by first = x days, second = x + 4 days; Work/day together = 1/x + 1/(x+4) = 1/12;
Solve: (2x+4)/(x(x+4)) = 1/12 → 24x + 48 = x² + 4x → x² – 20x – 48 = 0;
Solve quadratic → x = 24 (approx), other = 28 days.
उत्तर: मान लें पहला व्यक्ति = x दिन, दूसरा = x + 4 दिन; मिलकर कार्य/दिन = 1/x + 1/(x+4) = 1/12;
हल करें: (2x+4)/(x(x+4)) = 1/12 → 24x + 48 = x² + 4x → x² – 20x – 48 = 0;
हल करने पर x ≈ 24 दिन, दूसरा = 28 दिन।
Answer: Work/day A = 1/16, B = 1/24;
Work in 2 days (A+B) = 1/16 + 1/24 = (3+2)/48 = 5/48;
Work in 14 days = 7 cycles = 7 × 5/48 = 35/48;
Remaining = 13/48, next day A works = 1/16 = 3/48, Remaining = 10/48;
Next day B works = 1/24 = 2/48, Remaining = 8/48;
Next day A works again = 1/16 = 3/48, Remaining = 5/48;
Next day B works = 1/24 = 2/48, Remaining = 3/48;
Next day A works = 1/16 = 3/48, work finished;
Total days = 14 + 5 = 19 days.
उत्तर: A का दैनिक कार्य = 1/16, B = 1/24;
2 दिन में कार्य (A+B) = 1/16 + 1/24 = (3+2)/48 = 5/48;
14 दिन में कार्य = 7 चक्र = 7 × 5/48 = 35/48;
बचा = 13/48, अगले दिन A काम करता है = 1/16 = 3/48, बचा = 10/48;
अगले दिन B काम करता है = 1/24 = 2/48, बचा = 8/48;
फिर A = 3/48, बचा = 5/48;
फिर B = 2/48, बचा = 3/48;
फिर A = 3/48, पूरा हुआ;
कुल दिन = 14 + 5 = 19 दिन।
Answer: Work/day A+B+C = 1/10 + 1/15 + 1/20 = (6+4+3)/60 = 13/60;
Work done in 3 days = 3 × 13/60 = 39/60 = 13/20;
Remaining = 1 – 13/20 = 7/20.
उत्तर: दैनिक कार्य A+B+C = 1/10 + 1/15 + 1/20 = (6+4+3)/60 = 13/60;
3 दिन में किया गया कार्य = 3 × 13/60 = 39/60 = 13/20;
बचा कार्य = 1 – 13/20 = 7/20।
Answer: Work done in 6 days by A+B = 6 × (1/14 + 1/21) = 6 × (3/42 + 2/42) = 6 × 5/42 = 30/42 = 5/7;
Remaining = 1 – 5/7 = 2/7;
A alone rate = 1/14;
Time by A = (2/7) ÷ (1/14) = 4 days;
Total time = 6 + 4 = 10 days.
उत्तर: 6 दिन में A+B द्वारा कार्य = 6 × (1/14 + 1/21) = 6 × (3/42 + 2/42) = 6 × 5/42 = 30/42 = 5/7;
बचा कार्य = 1 – 5/7 = 2/7;
A की दर = 1/14;
A का समय = (2/7) ÷ (1/14) = 4 दिन;
कुल समय = 6 + 4 = 10 दिन।
Answer: Let A’s rate = a, B’s rate = b, C’s rate = c;
a + b = 1/9, b + c = 1/12, a + c = 1/18;
Adding all: 2(a + b + c) = 1/9 + 1/12 + 1/18 = (4/36 + 3/36 + 2/36) = 9/36 = 1/4;
So a + b + c = 1/8;
Subtract a + b from total: c = 1/8 – 1/9 = (9-8)/72 = 1/72 → C takes 72 days;
Similarly, A = 1/8 – 1/12 = (3-2)/24 = 1/24 → A takes 24 days;
B = 1/8 – 1/18 = (9-4)/72 = 5/72 → B takes 72/5 = 14.4 days.
उत्तर: मान लें A की दर = a, B = b, C = c;
a + b = 1/9, b + c = 1/12, a + c = 1/18;
सब जोड़ें: 2(a + b + c) = 1/9 + 1/12 + 1/18 = (4/36 + 3/36 + 2/36) = 9/36 = 1/4;
तो a + b + c = 1/8;
a + b घटाएं: c = 1/8 – 1/9 = (9-8)/72 = 1/72 → C = 72 दिन;
इसी तरह, A = 1/8 – 1/12 = (3-2)/24 = 1/24 → A = 24 दिन;
B = 1/8 – 1/18 = (9-4)/72 = 5/72 → B = 72/5 = 14.4 दिन।
Answer: Work done in 10 mins = 10(1/20 + 1/30) = 10(3/60 + 2/60) = 10 × 5/60 = 5/6;
Remaining = 1 – 5/6 = 1/6;
First pipe fills at 1/20 per min;
Time to fill remaining = (1/6) ÷ (1/20) = 20/6 = 3⅓ mins;
Total time = 10 + 3⅓ = 13⅓ minutes.
उत्तर: 10 मिनट में कार्य = 10(1/20 + 1/30) = 10(3/60 + 2/60) = 10 × 5/60 = 5/6;
बचा = 1 – 5/6 = 1/6;
पहला पाइप 1/20 प्रति मिनट भरता है;
बचा भरने का समय = (1/6) ÷ (1/20) = 20/6 = 3⅓ मिनट;
कुल समय = 10 + 3⅓ = 13⅓ मिनट।
Answer: Work/day A = 1/25, B = 1/15;
Work in 2 days (A+B) = 1/25 + 1/15 = (3+5)/75 = 8/75;
Work done in n cycles of 2 days = n × 8/75;
After 9 cycles (18 days), work done = 9 × 8/75 = 72/75 = 24/25;
Remaining = 1/25;
Next day A works and finishes remaining work in 1 day;
Total time = 18 + 1 = 19 days.
उत्तर: A का दैनिक कार्य = 1/25, B = 1/15;
2 दिन में कार्य (A+B) = 1/25 + 1/15 = (3+5)/75 = 8/75;
n चक्र में कार्य = n × 8/75;
9 चक्र (18 दिन) में कार्य = 9 × 8/75 = 72/75 = 24/25;
बचा = 1/25;
अगला दिन A काम करता है और 1 दिन में पूरा करता है;
कुल समय = 18 + 1 = 19 दिन।
Answer: Work/day A+B+C = 1/6 + 1/8 + 1/12 = (4+3+2)/24 = 9/24 = 3/8;
Work done in 2 days = 2 × 3/8 = 3/4;
Remaining work = 1 – 3/4 = 1/4;
Work/day A+B = 1/6 + 1/8 = (4+3)/24 = 7/24;
Time by A+B to finish = (1/4) ÷ (7/24) = (1/4) × (24/7) = 6/7 days ≈ 0.86 days;
Total time = 2 + 0.86 ≈ 2.86 days.
उत्तर: A+B+C दैनिक कार्य = 1/6 + 1/8 + 1/12 = (4+3+2)/24 = 9/24 = 3/8;
2 दिन में कार्य = 2 × 3/8 = 3/4;
बचा कार्य = 1 – 3/4 = 1/4;
A+B दैनिक कार्य = 1/6 + 1/8 = (4+3)/24 = 7/24;
A+B का समय = (1/4) ÷ (7/24) = (1/4) × (24/7) = 6/7 दिन ≈ 0.86 दिन;
कुल समय = 2 + 0.86 ≈ 2.86 दिन।
Answer: Work/day A+B = 1/20 + 1/25 = (5+4)/100 = 9/100;
Work done in 5 days = 5 × 9/100 = 45/100 = 9/20;
Remaining work = 1 – 9/20 = 11/20;
A alone rate = 1/20;
Time by A = (11/20) ÷ (1/20) = 11 days;
Total time = 5 + 11 = 16 days.
उत्तर: A+B का दैनिक कार्य = 1/20 + 1/25 = (5+4)/100 = 9/100;
5 दिन में किया गया कार्य = 5 × 9/100 = 45/100 = 9/20;
बचा कार्य = 1 – 9/20 = 11/20;
A की दर = 1/20;
A का समय = (11/20) ÷ (1/20) = 11 दिन;
कुल समय = 5 + 11 = 16 दिन।
Answer: Efficiency ratio A:B = 3:2;
Time ratio B:A = 3:2;
If A takes 20 days, B takes (3/2) × 20 = 30 days.
उत्तर: दक्षता अनुपात A:B = 3:2;
समय अनुपात B:A = 3:2;
यदि A 20 दिन लेता है, तो B = (3/2) × 20 = 30 दिन।
Answer: Let slower person take x days, faster takes x/2 days;
Work/day slower = 1/x, faster = 2/x;
Together = 1/x + 2/x = 3/x = 1/15;
So x = 45 days;
Slower = 45 days, faster = 22.5 days.
उत्तर: मान लें धीमा व्यक्ति = x दिन, तेज = x/2 दिन;
धीमे का दैनिक कार्य = 1/x, तेज का = 2/x;
साथ में = 3/x = 1/15;
तो x = 45 दिन;
धीमा = 45 दिन, तेज = 22.5 दिन।
Answer: Work/day A+B+C = 1/12 + 1/15 + 1/20 = (5+4+3)/60 = 12/60 = 1/5;
Work done in 3 days = 3 × 1/5 = 3/5;
Remaining work = 2/5;
Work/day B+C = 1/15 + 1/20 = (4+3)/60 = 7/60;
Time taken = (2/5) ÷ (7/60) = (2/5) × (60/7) = 24/7 ≈ 3.43 days.
उत्तर: A+B+C दैनिक कार्य = 1/12 + 1/15 + 1/20 = (5+4+3)/60 = 12/60 = 1/5;
3 दिन में किया गया कार्य = 3 × 1/5 = 3/5;
बचा कार्य = 2/5;
B+C का दैनिक कार्य = 1/15 + 1/20 = (4+3)/60 = 7/60;
समय = (2/5) ÷ (7/60) = (2/5) × (60/7) = 24/7 ≈ 3.43 दिन।
Answer: Filling rate = 1/15 + 1/20 = (4+3)/60 = 7/60 per minute;
Emptying rate = 1/30 per minute;
Net filling rate = 7/60 – 1/30 = 7/60 – 2/60 = 5/60 = 1/12 per minute;
Time to fill = 1 ÷ (1/12) = 12 minutes.
उत्तर: भरने की दर = 1/15 + 1/20 = (4+3)/60 = 7/60 प्रति मिनट;
खाली करने की दर = 1/30 प्रति मिनट;
शुद्ध भरने की दर = 7/60 – 1/30 = 7/60 – 2/60 = 5/60 = 1/12 प्रति मिनट;
भरने का समय = 1 ÷ (1/12) = 12 मिनट।
Answer: Work/day A+B+C = 1/10 + 1/12 + 1/15 = (6+5+4)/60 = 15/60 = 1/4;
Work done in 3 days = 3 × 1/4 = 3/4;
Remaining work = 1/4;
Work/day A+B = 1/10 + 1/12 = (6+5)/60 = 11/60;
Time by A+B = (1/4) ÷ (11/60) = (1/4) × (60/11) = 15/11 ≈ 1.36 days;
Total time = 3 + 1.36 ≈ 4.36 days.
उत्तर: A+B+C दैनिक कार्य = 1/10 + 1/12 + 1/15 = (6+5+4)/60 = 15/60 = 1/4;
3 दिन में किया गया कार्य = 3 × 1/4 = 3/4;
बचा कार्य = 1/4;
A+B का दैनिक कार्य = 1/10 + 1/12 = (6+5)/60 = 11/60;
A+B का समय = (1/4) ÷ (11/60) = (1/4) × (60/11) = 15/11 ≈ 1.36 दिन;
कुल समय = 3 + 1.36 ≈ 4.36 दिन।
Answer: Work/day A = 1/24, B = 1/30;
Work in 2 days (A+B) = 1/24 + 1/30 = (5+4)/120 = 9/120 = 3/40;
After 26 days (13 cycles), work done = 13 × 3/40 = 39/40;
Remaining work = 1 – 39/40 = 1/40;
On 27th day A works and completes 1/24 work, which is more than 1/40;
So total time ≈ 26 + (1/40) ÷ (1/24) = 26 + (1/40) × 24 = 26 + 0.6 = 26.6 days.
उत्तर: A का दैनिक कार्य = 1/24, B का = 1/30;
2 दिन का कार्य (A+B) = 1/24 + 1/30 = (5+4)/120 = 9/120 = 3/40;
26 दिन में (13 चक्र) किया गया कार्य = 13 × 3/40 = 39/40;
बचा कार्य = 1 – 39/40 = 1/40;
27वें दिन A काम करेगा और 1/24 कार्य करेगा, जो 1/40 से अधिक है;
कुल समय ≈ 26 + (1/40) ÷ (1/24) = 26 + (1/40) × 24 = 26 + 0.6 = 26.6 दिन।
Answer: 60% work = 12 days;
1% work = 12 ÷ 60 = 0.2 days;
100% work = 0.2 × 100 = 20 days.
उत्तर: 60% काम = 12 दिन;
1% काम = 12 ÷ 60 = 0.2 दिन;
100% काम = 0.2 × 100 = 20 दिन।
Answer: Work/day A+B = 1/18, A = 1/30;
B = 1/18 – 1/30 = (5 – 3)/90 = 2/90 = 1/45;
So B alone takes 45 days.
उत्तर: A+B का दैनिक कार्य = 1/18, A का = 1/30;
B = 1/18 – 1/30 = (5 – 3)/90 = 2/90 = 1/45;
अतः B अकेला 45 दिन लेगा।
Answer: Work/day A = 1/12, B = 1/15, C = 1/20;
Work done by A in total days = x days;
Work done in first 4 days by A+B+C = 4 × (1/12 + 1/15 + 1/20) = 4 × (5+4+3)/60 = 4 × 12/60 = 4 × 1/5 = 4/5;
Work done in next 2 days by A+C = 2 × (1/12 + 1/20) = 2 × (5+3)/60 = 2 × 8/60 = 2 × 2/15 = 4/15;
Total work done so far = 4/5 + 4/15 = (12/15 + 4/15) = 16/15 (more than 1, so work finishes before 6 days.)
Let A work total t days, then:
Work by A till finish = (1/12) × t;
Work by B for 4 days = 4 × 1/15 = 4/15;
Work by C for y days = y × 1/20;
Total work = 1;
Since B leaves after 4 days and C after y days (≤6), but from above, we assume C leaves exactly after 6 days:
Work done = A’s work in t days + B’s 4 days + C’s 6 days = 1;
(1/12)t + 4/15 + 6/20 = 1;
(1/12)t + 4/15 + 3/10 = 1;
(1/12)t = 1 – 4/15 – 3/10 = 1 – 8/30 – 9/30 = 1 – 17/30 = 13/30;
t = (13/30) × 12 = 13 × (12/30) = 13 × 0.4 = 5.2 days.
उत्तर: A का दैनिक कार्य = 1/12, B = 1/15, C = 1/20;
पहले 4 दिन A+B+C का कार्य = 4 × (1/12 + 1/15 + 1/20) = 4 × 12/60 = 4 × 1/5 = 4/5;
अगले 2 दिन A+C का कार्य = 2 × (1/12 + 1/20) = 2 × 8/60 = 4/15;
कुल कार्य = 4/5 + 4/15 = 16/15 (1 से अधिक, तो 6 दिन से पहले पूरा होगा);
मान लें A ने कुल t दिन काम किया;
B 4 दिन काम करता है = 4/15;
C 6 दिन काम करता है = 6/20 = 3/10;
कुल कार्य = 1/12 × t + 4/15 + 3/10 = 1;
1/12 t = 1 – 4/15 – 3/10 = 13/30;
t = 13/30 × 12 = 5.2 दिन।
Answer: Let B take x days; A takes x-10 days;
Efficiency of A = 1/(x-10), B = 1/x;
Together = 1/(x-10) + 1/x = x + (x-10)/(x(x-10));
Together’s time = x(x-10)/(2x-10).
उत्तर: मान लें B = x दिन, A = x-10 दिन;
A की दक्षता = 1/(x-10), B = 1/x;
साथ में = x + (x-10)/(x(x-10));
समय = x(x-10)/(2x-10)।
Answer: Work/day A = 1/15, B = 1/10;
Together = 1/15 + 1/10 = (2+3)/30 = 1/6;
Work done in 5 days = 5 × 1/6 = 5/6;
Remaining work = 1 – 5/6 = 1/6.
उत्तर: A का दैनिक कार्य = 1/15, B = 1/10;
साथ में = 1/15 + 1/10 = 1/6;
5 दिन में किया गया कार्य = 5 × 1/6 = 5/6;
बचा कार्य = 1 – 5/6 = 1/6।
Answer: Time for 3/5 work = 6 days;
Time for 1 work = 6 × (5/3) = 10 days;
Remaining work time = 10 – 6 = 4 days.
उत्तर: 3/5 काम में समय = 6 दिन;
1 काम का समय = 6 × (5/3) = 10 दिन;
बचा कार्य = 10 – 6 = 4 दिन।
Answer: Filling rate = 1/8, emptying rate = -1/12;
Net rate = 1/8 – 1/12 = (3-2)/24 = 1/24;
Time to fill = 24 hours.
उत्तर: भरने की दर = 1/8, खाली करने की दर = -1/12;
शुद्ध दर = 1/8 – 1/12 = 1/24;
भरने का समय = 24 घंटे।
Answer: Work/day A = 1/40, B = 1/60;
Together = 1/40 + 1/60 = (3+2)/120 = 1/24;
Work done in 10 days = 10 × 1/24 = 10/24 = 5/12;
Remaining work = 1 – 5/12 = 7/12;
Time for B = (7/12) ÷ (1/60) = 35 days.
उत्तर: A का दैनिक कार्य = 1/40, B = 1/60;
साथ में = 1/40 + 1/60 = 1/24;
10 दिन में किया गया कार्य = 10 × 1/24 = 5/12;
बचा कार्य = 1 – 5/12 = 7/12;
B का समय = (7/12) ÷ (1/60) = 35 दिन।
Answer: Work/day A = 1/25, B = 1/20;
Work in 2 days = 1/25 + 1/20 = (4+5)/100 = 9/100;
After 11 cycles = 11 × (9/100) = 99/100;
Remaining work = 1 – 99/100 = 1/100;
A takes (1/100) ÷ (1/25) = 0.25 days;
Total time = 22 + 0.25 = 22.25 days.
उत्तर: A का दैनिक कार्य = 1/25, B = 1/20;
2 दिन में कार्य = 1/25 + 1/20 = 9/100;
11 चक्र = 11 × 9/100 = 99/100;
बचा कार्य = 1 – 99/100 = 1/100;
A का समय = (1/100) ÷ (1/25) = 0.25 दिन;
कुल समय = 22 + 0.25 = 22.25 दिन।
Answer: Together = 1/10, A = 1/15;
B = 1/10 – 1/15 = (3-2)/30 = 1/30;
B alone takes 30 days.
उत्तर: साथ में = 1/10, A = 1/15;
B = 1/10 – 1/15 = 1/30;
B अकेला 30 दिन लेगा।
Answer: Efficiency of A = 1/50;
Efficiency of B = 1.25 × 1/50 = 1/40;
B takes 40 days.
उत्तर: A की दक्षता = 1/50;
B की दक्षता = 1.25 × 1/50 = 1/40;
B 40 दिन लेगा।
Answer: Together = 1/12, B = 1/20;
A = 1/12 – 1/20 = (5-3)/60 = 2/60 = 1/30;
Work ratio A:B = 1/30 : 1/20 = 2:3;
A’s share = (2/5) × 600 = ₹240.
उत्तर: साथ में = 1/12, B = 1/20;
A = 1/12 – 1/20 = 1/30;
कार्य अनुपात A:B = 2:3;
A का हिस्सा = (2/5) × 600 = ₹240।
Answer: Work/day A = 1/12, B = 1/16, C = 1/24;
Together = 1/12 + 1/16 + 1/24 = (2+3+4)/48 = 9/48 = 3/16;
Time = 16/3 ≈ 5.33 days.
उत्तर: A का दैनिक कार्य = 1/12, B = 1/16, C = 1/24;
साथ में = 1/12 + 1/16 + 1/24 = 3/16;
समय = 16/3 ≈ 5.33 दिन।